Geothermal Heat Pump Installation: Step-by-Step Process, Timeline and What to Expect

Short answer: installing a geothermal heat pump has two parts. Outside, a contractor installs the ground loop — vertical boreholes or horizontal trenches filled with pipe. Inside, the installer sets the heat pump in a utility room and connects it to your ducts or hydronic system and to your hot water. Before any of that happens, a proper project starts with a load calculation, a site evaluation and permits. Done well, the result is a system whose ground loop is expected to last 50+ years and whose indoor components can last up to 24 years, according to the US Department of Energy.

This guide walks through every step of a residential geothermal installation, what each one involves, how long it takes and the questions to ask your contractor.

The installation process at a glance

StepWhat happensWho does it
1. Load calculationRoom-by-room heating and cooling load (Manual J)Designer / HVAC contractor
2. Site evaluationSoil, geology, space, access, utilitiesGeothermal contractor / driller
3. System and loop designEquipment selection, loop type and lengthDesigner
4. PermitsDrilling, mechanical, electrical permits as requiredContractor
5. Loop installationDrilling or trenching, pipe, grout, headerDriller / excavator
6. Pressure test and flushingLeak test, purge air, fill with heat-transfer fluidContractor
7. Indoor installationHeat pump, piping, electrical, distributionHVAC / hydronic installer
8. CommissioningStartup, flow and temperature checks, controlsInstaller

Step 1: Load calculation and system sizing

Everything depends on how much heating and cooling your home actually needs. A room-by-room Manual J calculation sets the capacity of the heat pump and, just as importantly, the length of the ground loop. Oversizing adds loop length and cost; undersizing means more backup heat. Read our guide to geothermal heat pump sizing before you compare quotes.

Step 2: Site evaluation

The contractor looks at the land and the ground to decide which kind of loop fits. According to the DOE, an accredited contractor determines the best system partly by evaluating the site’s soil and ground makeup. Typical checks include:

  • Available land and where a drill rig or excavator can reach.
  • Soil and rock type, which affect drilling cost and how well the ground transfers heat.
  • Groundwater, if an open-loop system is being considered.
  • Buried utilities, septic systems, wells and property lines.
  • For larger projects, a thermal conductivity test of a test borehole.

Step 3: Choosing the loop type

Loop typeHow it worksBest for
Vertical closed loopBoreholes about 4 inches in diameter, roughly 20 feet apart and 100–400 feet deep (DOE)Small lots, retrofits, commercial
Horizontal closed loopPipe in trenches at least 4 feet deep (DOE)Homes with plenty of open land
Pond/lake loopCoils submerged in a body of water; at least 8 feet below the surface in cold climates (DOE)Properties with a suitable pond or lake
Open loopUses well water directly and returns it to the ground or surfaceSites with abundant, good-quality groundwater where allowed

Vertical loops cost more per foot but need little land. Horizontal loops are usually cheaper to install where space allows. Compare them in vertical geothermal loops: costs and when to choose them.

No room for a loop at all? Ecoforest also pairs its ecoGEO+ units with the AU Neo dry cooler, an outdoor heat exchanger that lets the same indoor unit work without boreholes — or in a hybrid setup with a ground loop added now or later.

Step 4: Permits

Requirements vary by state and municipality. Depending on where you live, a project may need drilling or well permits, a mechanical permit for the heat pump and an electrical permit. Your contractor should advise on any regulations or permits required and handle the applications.

Step 5: Installing the ground loop

Vertical loops

A drill rig bores each hole, a U-shaped loop of high-density polyethylene pipe is inserted, and the borehole is filled with grout to ensure good thermal contact and protect groundwater. The loops are then joined in a header and run in a trench to the house.

Horizontal loops

An excavator or trencher digs the trenches, the pipe is laid out (straight or in coils, depending on the design) and the trenches are backfilled.

Expect heavy equipment on site and some disruption to the yard. Landscaping is usually restored at the end, which is one reason geothermal is easiest in new construction.

Step 6: Pressure testing, flushing and filling

Before the loop is buried or connected, it should be pressure-tested for leaks. It is then flushed and purged of air and filled with the heat-transfer fluid specified by the designer (water or a water-antifreeze mix, depending on the climate). This step matters: air or debris left in the loop reduces efficiency and can damage the circulating pumps.

Step 7: Installing the heat pump indoors

The heat pump goes in a basement, garage or utility room. The installer connects it to the ground loop, the distribution system, the domestic hot water and the electrical supply. There is no outdoor condensing unit.

  • Ducted homes: a water-to-air unit or the ecoGEO+ WWA, which delivers air through ducts and water to radiant floors from one unit.
  • Hydronic homes: a water-to-water unit such as the ecoGEO+ Basic, feeding radiant floors, fan coils or radiators. See hydronic vs. forced-air heat pumps.
  • Tight spaces: the ecoGEO+ Compact includes a 43-gallon stainless steel hot water tank and takes about 10 square feet.

All-in-one units save installation labor: the ecoGEO+ Basic and Compact come with the circulating pumps, expansion vessels, hot water valve, backup heater and controls built in, so there are fewer components to fit and wire on site.

Step 8: Commissioning

At startup, the installer verifies loop and building flow rates, entering and leaving water temperatures, refrigerant-side operation, controls and safety devices, and sets up the thermostat or app. Ask for a written commissioning report — it becomes the baseline for future maintenance.

How long does a geothermal installation take?

It depends on the loop type, ground conditions, permit timelines and whether it’s new construction or a retrofit. Drilling or trenching for a typical home is often a matter of days, and the indoor work a few more. Design and permitting usually take longer than the physical work, so plan ahead — especially if you want the system running before the heating season.

What does installation cost?

The ground loop is usually the largest single cost, followed by the heat pump and the indoor work. The DOE notes that installation can cost several times as much as an air-source system of the same capacity, with the extra cost often recovered through energy savings in roughly 5 to 10 years, depending on energy prices and incentives. For a detailed breakdown, see how much geothermal costs for a house, and check which incentives still apply in our geothermal tax credit 2026 guide.

Questions to ask a geothermal installer

  • Will you perform a room-by-room Manual J load calculation?
  • How was the loop length calculated, and what soil assumptions did you use?
  • Who does the drilling, and are they licensed and insured where required?
  • Is the installer accredited (for example by IGSHPA) and experienced with this equipment?
  • How will the loop be pressure-tested, flushed and documented?
  • What does commissioning include, and will I get a report?
  • What warranty covers the loop, the equipment and the labor?

Frequently asked questions

Can geothermal be installed in an existing home?

Yes. Vertical loops need little space, and the heat pump can usually connect to existing ducts or hydronic piping, although some upgrades may be needed.

How deep are geothermal wells?

Vertical boreholes are typically 100 to 400 feet deep, according to the DOE. The exact depth and number depend on the load and the ground.

Does a geothermal system need an outdoor unit?

No. The heat pump is installed indoors and the loop is underground, so there is no outdoor condenser.

Will installation damage my yard?

There will be temporary disruption from drilling or trenching. Vertical loops disturb less area than horizontal ones, and the site is normally restored afterwards.